MAKING WAY

October 30, 2012

Post & Mail photo / Brianne Eichman

Bridge construction is moving forward on the Morsches Park Blue River Trail extension project. According to Columbia City Community Development Director Jeff Walker, bridge construction began Oct. 23. A bearing beam was placed on the three helicals on each end of the bridge at the embankment. The two main “I” beams were then set on the bearing beams as the braces were connected. Pictured is the recent construction made on the side railing and the bridge deck.